Timeline
We have set a very ambitious timeline in order to maximize the current excitement about this project.
Starting Summer 2025
Stage 1: 50m Pool (10 lanes long course, 22 lanes short course)
This stage includes the pool, pump house, deck, fencing, etc.
Breaking ground: June 2025
Estimated Completion (due to rainy season): November 2025
Here’s what has to happen before we break ground:
✅ Land survey already completed by the foundation
Architectural & Civil Plans (April)
Geotech drilling (April)
Finish fundraising for this stage
Stage 1.5: Updating Current Building
This stage includes facelift to current building facade, updating locker rooms, adding hot water to showers, etc.
Start Date: November 2025
Estimated Completion: January 2026
Here’s what has to happen before we start this stage:
City approval of renovation plans
Finish fundraising for the stage
Stage 2: Historic Green Space
This stage includes updated landscaping, picnic tables, large-scale sculptures from local artists, etc.
Start Date: December 2025, 2025
Estimated Completion: February 2026
Here’s what has to happen before we start this stage:
Landscape architectural designs
Call for artists
Finish fundraising for the stage
Stage 3: Beach Volleyball Courts
This stage includes the 3 beach volleyball courts and stands.
Start Date: December 2025.
Completion Date: January 2025.
Here’s what has to happen before we break ground:
✅ Land survey already completed by the foundation
✅ Ordering pro-quality net and equipment: already comleted by the City
Get approval from board to start: THIS HAS NOT BEEN GRANTED YET